Snagging: checking finished work before handover

“Snagging” is the process of checking finished work for defects and incomplete items before handover. The list that comes out of it, the snag list, is the builder’s last to-do list. Done properly, it means you move into a home that is finished, not nearly finished.

When to snag

Snagging usually happens when the builder says the work is practically complete. Walk the house with the site manager and, on larger projects, the architect. Go in daylight, with good lighting, and allow plenty of time. A house is easier to inspect when it is empty and clean.

How to snag

  • Take a notebook or use your phone, and photograph each item
  • Work methodically room by room, top to bottom: ceiling, walls, windows, doors, floor, fittings
  • Use a small piece of tape to mark each snag
  • Test everything that moves, opens, switches or runs water
  • Be specific: “scratch on bedroom 2 door, outside face” is better than “doors need touching up”

What to check

Walls and ceilings

  • Paint coverage, drips and patchy areas
  • Cracks, visible joints in ceilings and uneven plaster
  • Clean lines where colours meet

Doors and windows

  • Open and close every door and window. Do they swing freely and close properly?
  • Check locks and handles, and that keys work
  • Look for scratches on frames and glass
  • Check sealant around frames, inside and outside

Floors

  • Cracked, chipped or hollow-sounding tiles (tap them)
  • Grout gaps and uneven joints
  • Scratches on timber floors
  • Skirtings fixed and finished

Kitchen and joinery

  • Doors aligned and gaps even
  • Drawers run smoothly and close softly
  • Worktop joints and edges
  • Appliances installed and working

Bathrooms

  • Run every tap, shower and bath. Check hot and cold.
  • Check water drains away quickly and does not pond in showers
  • Flush toilets and check for leaks underneath basins
  • Silicone neat and complete
  • Extractor fans working

Electrical

  • Every light switch and plug point works
  • Covers straight and clean
  • Distribution board labelled

Outside

  • Gutters and downpipes complete and connected
  • Paving falls away from the house
  • Gates, garage doors and motors working
  • Site cleared of rubble and materials

Documents to receive

  • Electrical certificate of compliance
  • Plumbing certificate of compliance and geyser installation certificate
  • Gas certificate of conformity, if applicable
  • Glazing certificate
  • Roof truss and waterproofing certificates and guarantees, if applicable
  • Engineer’s completion certificates for structural work
  • Occupation certificate from the City, where applicable
  • NHBRC enrolment documents for new homes
  • Manuals and warranties for appliances and equipment

After handover

Some defects only show up after you have lived in a house for a while: small cracks as the building settles, a door that sticks in winter. That is what the defects liability period is for. Keep a list and give it to your builder at the agreed time.

Our approach

We do our own internal snag before we invite clients to inspect, so the list you create should be short. If you are getting close to the end of a project with us, we will set a time to walk through it together. If you want to know more about how we finish projects, ask us.